Final Silver Line Timetable Has Rail on Track

Phase 1 of new rail line expected to be turned over for testing and training in August.

Metro's Silver Line Phase 1 is 86 percent complete and on schedule for delivery by the end of August, says Pat Nowakowski, Executive Director of the Dulles Corridor Metrorail Project.

Nowakowski gave an analysis at last week's Metropolitan Washington Airports Authority meeting.

MWAA is not giving an exact date that Phase 1 of the Silver Line — which will run from Tysons Corner to Reston's Wiehle Avenue — will open, but is sticking with a general date of December 2013 for now, MWAA spokesman Rob Yingling said.

Some of the highlights of Nowakowski's presentation:

* Final Design – All design is complete. One permit needs to be secured.

* Metro has paid out $2.255 billion so far. The final cost is expected to be $2,905,695,000. There is $81 million in contingency remaining.

* Turnover in late August will happen when: All construction complete; all testing complete; all as-built drawings complete (one still remains to be done); all maintenance manuals are provided; all supplier training is complete; all certification documents are complete; and the West Falls Church Yard is complete (expected Dec. 20, 2013).

* After that, operational readiness, inspection and turnover activties will begin with an expected operation date 90 days later.

* For Phase 2, which will run from Wiehle Avenue to Dulles International Airport and into Loudoun County, MWAA expects to award a construction contract by April 2013.

To see Nowakowski's presentation, click here.

Eric Paul Gioia January 23, 2013 at 07:09 PM
one step closer to dulles being connected after all of these years.
Rob Whitfield January 24, 2013 at 12:01 PM
Karen, somehow you omitted to mention that most Series 7000 railcars will not be delivered for Silver Line use until July 2014 at the earliest. WMATA will have four "test" cars for use during the first half of 2014 but wants to use them throughout the Metrorail system. Even though Metrorail riders are paying next to nothing of the $6 billion costs of the Silver Line, riders from the Dulles Corridor will share equally in use and enjoyment of the original 35+ year old Series 1000 rail cars -which were deemed unsafe by the National Transportation Safety Board before the 2009 Red Line crash. WMATA has never responded to most fundamental problems facing Dulles Rail or provided detailed information on projected fares, ridership, operating revenues, costs and who will pay replacement costs for railcars and other equipment together with the assumptions and data to support projections. The delay at West Falls Church maintenance yard is no exception. To date, WMATA has offered no explanation as to why Dulles Toll Road users should pay a majority of the costs of the planned Dulles Maintenance yard which is designed to service not only the planned 128 Silver Line cars but an additional 300 cars on order to replace the Series 1000 rail cars. It appears that our politicians, both in Richmond and Washington, DC are either complicit in this apparent fraud or too lazy to do anything to protect Virginia taxpayers. It is time for WMATA oversight investigations.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »